North Bridge Update

  • Aug 15, 2017

This important project began a year and a half ago and it still remains on time and on budget with everything scheduled to be completed by October 2018!

On the North Bridge, the structural steel for the west half of the bridge is in place and work is ongoing on the final in-river pier. Once the final pier is finished, the structural steel for the east half of the bridge will be installed. Crews are also installing deck panels on the west half of the bridge.

Thank you for your patience during the construction process for all of the other parts of this project including new roads and upgrades to existing ones.  The twinning of Central Avenue north of Attridge is continuing, and the McOrmond Drive extension is well underway.
For more North Bridge project updates, please visit: www.newnorthbridge.ca